The main activities for the construction of the gas interconnector Greece – Bulgaria (the IGB pipeline) are being carried out at a good pace, over 90 km of the entire route are now completely ready

By
BLACKSEA-CASPIA

The implementation of the Greece-Bulgaria interconnector continues at a good pace, and all major project implementation activities have progressed significantly since the beginning of the year despite the complicated situation related to the COVID-19 pandemic. By the end of May, the welded sections of the pipeline have reached 145 km of the total length of the 182-kilometer route. The terrain is completely cleared, over 170 km of pipes have been distributed on site in preparation for further activities.